Thanks to our significant experience working with the main constructors in the world, we have been following the evolution of materials for more than 20 years. For this reason we are specialized in the converson of automated progams, the goal being to bring to update them from older versions to the most recent one.
In these last years, we have successfully realized dozens of hardware and software migrations : each time with the same challenge of minimizing both risk and downtime so the client can be back into production in record time.
To do this and to respond to growing demand, we have developped several tools that allow us to realize software & hardware migrations regardless of the language in use.
Project with more than 250 input/outputs
Program longer than 5 000 lines of code
Several dozen inter-PLC messages in a network of 10 PLC
More than 600 errors after conversion with the constructor’s utility.
After phases of study, preparation and testing, we proceeeded to the migration of our client’s PLC Program in record time. Less than 6 hours later, the first production lines were starting. By the end of the day (12 hours after production was stopped), the entire installation was working and « returned » to the client. All the automated supervision of the installation was working perfectly with the new PLC.