Fuel Loading bridge – EPR – FINLAND

For nearly a year, our team of automation engineers worked on the commissioning of the fuel loading bridge for the EPR in Olkiluoto, Finland.

The following nuclear equipments were commissioned :

– AC : Auxiliary Crane

– SFMB : Spent Fuel Mast Bridge

– RM : Refueling Machine

They programmed the SIL3 safety PLCs and monitored the nuclear certification of the different pieces of equipment.  To respond to our client’s specific needs, we also provided technical assistance during the start-up phase.

The Key Elements :

  • SIL3 Safety Automation
  • 260 days of Technical Assistance
  • Certified Nuclear Equipment

#IESAAutomation #Automation #SafetyAutomation #SIL3 #NuclearCertification #Commissioning #Nuclear #EPR #AuxiliaryCrane #NewFuelElevator#SpentFuelMastBridge #FuelTransferFacility #RefuelingMachine #NuclearFuelLoading #SafetyPLC #SafetyIntegrityLevel