We worked on the power management control system of the FPSO Dalia in Angola.
In particular, we designed, programmed and installed the PLC system, for which we also supplied the electric cabinets. After 1750 engineering hours, 3000 programming hours and nearly 800 hours of tests (FAT and SAT), the vessel was set off to sea on its first mission.
This technical challenge allowed us to demonstrate our skills in terms of reactivity, productivity and adaptability.
Key contributions:
- 3,000 hours of programming and tests
- 7,500 database points
- 600 cabled input/outputs
- 3,700 network input/outputs