The Arzew refinery’s Electrical Control System in Algeria

We worked on the Arzew refinery’s Electrical Control System in Algeria.

In particular we designed, programmed and installed the SNCC – PCS7 system, for which we also provided the electrical cabinets.  After 2,500 engineering hours, 5,000 programming hours and nearly 1,500 hours of tests (FAT and SAT), the process commissioning phase has been carried out.

Key Contributions :

  • 5,000 cabled I/O
  • 30,000 network I/0
  • 50,000 database points
  • 2,500 communicating components connected