We have worked on the transitic system of a tire factory in France.
After having realized the site survey, we have integrated the new programming standards and then simulated the control-command system of the process.
We have also converted 10 PLC5 programs to ControlLogix. It represents 2100 Input/Output.
Our team carried out the commissioning phase and trained operators of the new installation.
The Key Elements :
- Conversion of PLCs programs
- Simulation of the control system
- Replacement of 10 PLC5 by 10 ControlLogix
- 2100 Input/Output